OPEC Open-Path Eddy-Covariance System
FIGURE 4-2. LoggerNet station setup for the “ts_data” table
In the “Schedule” tab, configure the station’s data collection as shown in
FIGURE 4-3. Modify the Primary Retry Interval, Number of Primary Retries,
and the Secondary Retry interval as needed for the specific telecommunications
option used at the station. For example, a site using Freewave spread spectrum
radios or an Ethernet connection may require a long interval between retries or
more frequent retry attempts because of other background traffic.
FIGURE 4-3. LoggerNet station data collection schedule